AIA Document A101 — 2017
Standard Form of Agreement Between Owner and Contractor where the basis of
payment is a Stipulated Sum
AGREEMENT made as of the 26th day of February in the year 2025
(In words, indicate day, month and year.) ADDITIONS AND DELETIONS:
The author of this document has
BETWEEN the Owner: added information needed for its
(Name, legal status, address and other information) completion. The author may also
have revised the text of the original
City of Muskegon AIA standard form. An Additions and
Deletions Report that notes added
933 Terrace Street
information as well as revisions to the
Muskegon, MI 49440
standard form text is available from
Kenneth D. Johnson, Mayor
the author and should be reviewed. A
vertical line in the left margin of this
and the Contractor:
document indicates where the author
(Name, legal status, address and other information)
has added necessary information
and where the author has added to or
Muskegon Quality Builders, inc.
deleted from the original AIA text.
2837 Peck Street
Muskegon Heights, MI 49444 This document has important legal
Thomas A. Grimm, President consequences. Consultation with an
' attorney is encouraged with respect
for the following Project: to its completion or modification.
(Name, location and detailed description) The parties should complete
A101®-2017, Exhibit A, Insurance
Muskegon Police Department - First Floor Office Renovatipns and Bonds, contemporaneously with
933 Terrace Street this Agreement. AIA Document
Muskegon, Michigan 49440 A201@-2017, General Conditions of
the Contract for Construction, is
The Architect: adopted in this document by
(Name, legal status, address and other information) reference. Do not use with other
general conditions unless this
Concept Design Studio, Inc. document is modified.
800 E. Ellis Road, Suite 508
Muskegon, Michigan 49441
Alan M Majeski AIA
The Owner and Contractor agree as follows.
AIA Document A101 — 2017. Copyright© 1915, 1918, 1925, 1937, 1954, hile 41961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights
Init. reserved. “The American Institute of Architects,” “American Institute of Archi cts,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The 1
American Institute of Architects. This document was produced at 11:22:19 Ef on 02/26/2025 under Order No.2114607688 which expires on 02/25/2026, is not for
resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations,
e-mail docinfo@aiacontracts.com.
User Notes: (1448228681)
TABLE OF ARTICLES
4 THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
EXHIBITA INSURANCE AND BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other
Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed
in this Agreement, and Modifications issued after execution|of this Agreement, all of which form the Contract, and are
as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire
and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements,
either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in
the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 3.1 The date of commencement of the Work shall be:
(Check one of the following boxes.)
| [X] The date of this Agreement.
{ ] A date set forth in a notice to proceed issued by the Owner.
{ ] Established as follows:
(Insert a date or a means to determine the date of commencement of the Work.)
Ifa date of commencement of the Work is not selected, then the date of commencement shall be the date of this
Agreement.
§ 3.2 The Contract Time shall be measured from the date of commencement of the Work.
§ 3.3 Substantial Completion
§ 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, ihe Contractor shall
achieve Substantial Completion of the entire Work:
(Check one of the following boxes and complete the necessury information.)
AIA Document A101 — 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1987, 1974, 1977, 1987, 1991, 1997, 2007 and 2017, All rights
Init. reserved. “The American Institute of Architects,” “American Institute of Architects,” "AIA,” the AIA Logo, and "AIA Contract Documents" are trademarks of The
American Institute of Architects. This document was produced at 11:22:19 ET on 02/26/2025 under Order No.2114607688 which expires on 02/25/2026, is not for
i resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations,
e-mail docinfo@aiacontracts.com.
User Notes: (1448228681)
{ | Not later than ( ) calendar days from the date of commencement of the Work.
| [X].__ By the following date: June 27, 2025
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are
to be completed prior to Substantial Completion of the entife Work, the Contractor shall achieve Substantial
Completion of such portions by the following dates:
Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Comple tion as provided in this Section 3.3, liquidated damages, if
any, shall be assessed as set forth in Section 4.5.
ARTICLE 4 CONTRACT SUM
§ 4.1 The Owner shall pay the Contractor the Contract Sunj in current funds for the Contractor’s performance of the
Contract. The Contract Sum shall be Two Hundred Eight Seven Thousand - One Hundred Thirty Dollars G6
287,130.00 ), subject to additions and deductions as provided in the Contract Documents.
§ 4.2 Alternates
§ 4.2.4 Alternates, if any, included in the Contract Sum:
Item Price
§ 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following
execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement.
(Insert below each alternate and the conditions that must be metfor the Owner to accept the alternate.)
Item Price Conditions for Acceptance
§ 4.3 Allowances, if any, included in the Contract Sum:
(Identify each allowance.)
Item Price
Bond Cost $2,630.00
§ 4,4 Unit prices, if any:
(Identify the item and state the unit price and quantity limitations, ifany, to which the unit price will be applicable.)
Item Units and Limitations Price per Unit ($0.00)
§ 4.5 Liquidated damages, if any:
(Insert terms and conditions for liquidated damages, if any
§ 4.6 Other:
(Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.)
AIA Document A101 — 2017, Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991,Documents” 1997, 2007 and 2017. All rights
Init. reserved. "The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract are trademarks of The 3
American {Institute of Architects. This document was produced at 11:22:19 Ef on 02/26/2025 under Order No.2114607688 which expires on 02/25/2026, Is not for
i resale, Is ficensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations,
e-mail docinfo@aiacontracts.com,
User Notes: (1448228681)
ARTICLE 5 PAYMENTS
§ 5.4 Progress Payments
§ 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for
Payment issued by the Architect, the Owner shall make pr gress payments on account of the Contract Sum to the
Contractor as provided below and elsewhere in the Contra¢ t Documents.
§ 5.1.2 The period covered by each Application for Paymet t shall be one calendar month ending on the last day of the
month, or as follows:
§ 5.1.3 Provided that an Application for Payment is receive i by the Architect not later than the 4th day of a month, the
Owner shall make payment of the amount certified to the C ontractor not later than the 30th day of the same month. If
an Application for Payment is received by the Architect aft er the application date fixed above, payment of the amount
certified shall be made by the Owner not later than twenty pne (21) days after the Architect receives the Application
for Payment.
(Federal, state or local laws may require payment within a certain period of time.)
§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor
in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the
various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to
substantiate its accuracy, as the Architect may require. Thi schedule of values shall be used as a basis for reviewing
the Contractor’s Applications for Payment.
§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of
the period covered by the Application for Payment.
§ 5.1.6 In accordance with AIA Document A201TM-2017, General Conditions of the Contract for Construction, and
subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as
follows:
§ 5.1.6.1 The amount of each progress payment shall first i nclude:
‘1 That portion of the Contract Sum properly a {locable to completed Work;
2 That portion of the Contract Sum properly a locable to materials and equipment delivered and suitably
stored at the site for subsequent incorporatio h in the completed construction, or, if approved in advance
by the Owner, suitably stored off the site at a location agreed upon in writing; and
3 That portion of Construction Change Direct ves that the Architect determines, in the Architect’s
professional judgment, to be reasonably jus ified.
§ 5.1.6.2 The amount of each progress payment shall then be reduced by:
1 The aggregate of any amounts previously pdid by the Owner;
2. The amount, if any, for Work that remains uncorrected and for which the Architect has previously
withheld a Certificate for Payment as provided in Article 9 of AIA Document A201-2017;
3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier,
unless the Work has been performed by others the Contractor intends to pay;
4 For Work performed or defects discovered since the last payment application, any amount for which
the Architect may withhold payment, or null fy a Certificate of Payment in whole or in part, as provided
in Article 9 of AIA Document A201-2017; and
5 Retainage withheld pursuant to Section 5.1.7.
§ 5.1.7 Retainage
§ 5.1.7.1 For each progress payment made prior to Substan ial Completion of the Work, the Owner may withhold the
following amount, as retainage, from the payment otherwise due:
(Insert a percentage or amount to be withheld as retainage|from each Application for Payment. The amount of
retainage may be limited by governing law.)
AIA Document A101 — 2017. Copyright © 1915, 1918, 1925, 1937, 1954, 19 8, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights
Init. reserved. “The American Institute of Architects," “American institute of Archit acts,” “AIA," the AIA Logo, and “AIA Contract Documents” are trademarks of The
American institute of Architects. This document was produced at 11:22:19 E yb on 02/26/2025 under Order No.2114607688 which expires on 02/25/2026, is not for
resale, Is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations,
e-mail docinfo@aiacontracts.com,
User Notes: (1448228681)
§ 5.1.7.4.1 The following items are not subject to retainage:
(Insert any items not subject to the withholding of retainage, such as general conditions, insurance, etc,)
Bond Costs
§ 5.1.7.2 Reduction or limitation of retainage, if any, shall be as follows:
Substantial Completion of the entire Work,
(if the retainage established in Section 5.1. 7.1 is to be modified prior toWork
including modifications for Substantial Completion ofportions of the as provided in Section 3.3.2, insert
provisions for such modifications.)
§ 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Substantial Completion of the Work, the Contractor may
Payment pursuant
submit an Application for Payment that includes the retainage withheld from prior Applicati notforinclude
ons
to this Section 5.1.7. The Application for Payment submitted at Substantial Completion shall retainage as
follows:
(Insert any other conditions for release of retainage upon Substantial Completion.)
of the Contractor, the Owner shall pay
§ 5.1.8 If final completion of the Work is materially delayed through no faultDocumen
the Contractor any additional amounts in accordance with Article 9 of AJA t A201-2017.
§ 5.1.9 Except with the Owner’s prior approval, the Contrattor shall not make advance payments to suppliers for
materials or equipment which have not been delivered and stored at the site.
§ 5.2 Final Payment
§ 5.2.1 Final payment, constituting the entire unpaid balande of the Contract Sum, shall be made by the Owner to the
Contractor when
‘4 correct
the Contractor has fully performed the Contract except for the Contractor’s responsibility to ts,
Work as provided in Article 12 of AIA Document A201-2017, and to satisfy other requiremen ifany,
which extend beyond final payment; and
2 afinal Certificate for Payment has been issued by the Architect.
§ 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the
Axchitect’s final Certificate for Payment, or as follows:
§ 5.3 Interest
Payments due and unpaid under the Contract shall bear int¢rest from the date payment is due at the rate stated below,
or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located,
(Insert rate of interest agreed upon, if any.)
%
ARTICLE 6 DISPUTE RESOLUTION
§ 6.1 Initial Decision Maker
The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA DocumentDecision A201-2017, unless the
parties appoint below another individual , not a party to this Agreemen t, to serve as the Initial Maker.
(If the parties mutually agree, insert the name, address and other contact informati on of the Initial Decision Maker, if
other than the Architect.)
AIA Document A101 — 2017, Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 4961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007are and 2017. All rights
reserved. "The American Institute of Architects,” “American Institute of Arch tects,” “AIA,” the AIA Logo, and “AIA Contract Documents” trademarks of The
Init.
American institute of Architects. This document was produced at 11:22:19 BT on 02/26/2025 under Order No.211460768 8 which expires on 02/25/2026, is not for
violations,
resale, is licensed for one-time use only, and may only be used In accordanke with the AIA Contract Documents® Terms of Service. To report copyright
e-mail docinfo@aiacontracts.com,
User Notes: (1448228681)
§ 6.2 Binding Dispute Resolution
For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201-2017, the
method of binding dispute resolution shall be as follows:
(Check the appropriate box.)
[X] Arbitration pursuant to Section 15.4 ofAIA Document A201-2017
[ ] Litigation in a court of competent jurisdiction
{ ] Other (Specify)
do not subsequently agree in
If the Owner and Contractor do not select a method of bind ing dispute resolution, orresolved by litigation in a court of
writing to a binding dispute resolution method other than li Ligation, Claims will be
competent jurisdiction.
ARTICLE 7 TERMINATION OR SUSPENSION
in Article 14 of AIA Document
§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided
A201-2017.
§ 7.1.1 If the Contract is terminated for the Owner’s convehience in accordan ce with Article 14 of AIA Document
A201-2017, then the Owner shall pay the Contractor a termination fee as follows:
torfollowing a termination for
(Insert the amount of, or methodfor determining, the fee, i any, payable to the Contrac
the Owner’s convenience.)
17.
§ 7.2 The Work may be suspended by the Owner as provid ed in Article 14 of ALA Document A201-20
ARTICLE 8 MISCELLANEOUS PROVISIONS
of AIA Document A201-2017 or another Contract
§ 8.1 Where reference is made in this Agreement to a provisioorn supplem
Docutnent, the reference refers to that provision as amended ented by other provisions of the Contract
Documents.
§ 8.2 The Owner’s representative:
(Name, address, email address, and other information)
Lt. Bryan Prindle
City of Muskegon Police Department
980 Jefferson Street
Muskegon, Michigan 49443
bryan .prindle@shorelinecity.com
§ 8.3 The Contractor’s representative:
(Name, address, email address, and other information)
Thomas A. Grimm, President
Muskegon Quality Builders, Inc.
2837 Peck Street
Muskegon, Heights, Michigan 4944X4
thom@mabinc.com
§ 8.4 Neither the Owner’s nor the Contractor’s representa ive shall be changed without ten days’ prior notice to the
other party.
‘AIA Document A101 — 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1356, 4961, 1963, 1967, and 2017. All tights
1974, 1977, 1987, 1991, 1997, 2007are
American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” trademarks of The
Init. reserved. “The was produced at 11:22:19 E T on 02/26/2025 under Order No.2114607688 which expires on 02/25/2026, is not for
violations,
resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright
American Institute of Architects. This document
e-mail docinfo@aiacontracts.com. (1448228681)
User Notes:
§ 8.5 Insurance and Bonds
§ 8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document
A101TM_2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a
Stipulated Sum, Exhibit A, Insurance and Bonds, and elsewhere in the Contract Documents.
§ 8.5.2 The Contractor shall provide bonds as set forth in ALA Document A101TM—2017 Exhibit A, and elsewhere in
the Contract Documents.
§ 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A201—2017, may be given in accordance
with a building information modeling exhibit, if completed, or as otherwise set forth below:
(if other than in accordance with a building information moreling exhibit, insert requirementsfor delivering notice in
electronic format such as name, title, and email address of the recipient and whether and how the system will be
required to generate a read receipt for the transmission.)
§ 8.7 Other provisions:
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
§ 9.1 This Agreement is comprised of the following documents:
41. AIA Document A101TM-2017, Standard Fotm of Agreement Between Owner and Contractor
2 ATA Document A101TM 2017, Exhibit A, Insurance and Bonds
3 ATA Document A201TM_2017, General Confitions of the Contract for Construction
4 Building information modeling exhibit, dated as indicated below:
(Insert the date of the building information modeling exhibit incorporated into this Agreement.)
a
5 Drawings — See attached Drawing Index
Number Title Date
6 Specifications — See attached Specification index
Section Title Date Pages
7 Addenda, if any:
Number Date Pages
Addendum #01 January 31, 2025 i
Addendum #02 February 10, 2025 1
Portions of Addenda relating to bidding or proposal requirements are not part of the Contract
Documents unless the bidding or proposal requirements are also enumerated in this Article 9.
8 = Other Exhibits:
(Check all boxes that apply and include appropriate information identifying the exhibit where
required.)
[ ] AIA Document E204TM~2017, Sustainable Projects Exhibit, dated as indicated below:
(Insert the date of the E204-2017 i 2corporated into this Agreement.)
AIA Document A101 ~ 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967,Logo, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. Alt rights
init. reserved. “The American Institute of Architects,” “American Institute of Architects,” "AIA," the AIA and “AIA Contract Documents” are trademarks of The
is not for
American Institute of Architects. This document was produced at 11:22:19 BT on 02/26/2025 under Order No.2114607688 which expires on 02/25/2026,violations,
/ resale, is licensed for one-time use only, and may only be used In accordan¢e with the AIA Contract Documents® Terms of Service. To report copyright
e-mail docinfo@aiacontracts.com.
User Notes: (1448228681)
[ ] The Sustainability Plan:
Title Date Pages
[ ] Supplementary and other Conditions of the Contract:
Document Titl e Date Pages
9 Other documents, if any, listed below:
(List here any additional documents that are intended to form part of the Contract Documents. AIA
Document A201TM2017 provides that the allvertisement or invitation to bid, Instructions to Bidders,
sample forms, the Contractor's bid or propasal, portions ofAddenda relating to bidding or proposal
requirements, and other information furnished by the Ownerin anticipation of receiving bids or
proposals, are not part of the Contract Doci ments unless enumeratedin this Agreement. Any such
documents should be listed here only if intended to be part of the Contract Documents.)
This Agreement entered into as of the day and year first wilitten above.
‘Kei IAD Ve Armee CONTRACTOR (Signature)
Kenneth D. Johnson, on
OWNER (Signature)
Thomas A. Grimm, President
(Printed name and title) (Printed name and title)
— 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 19 58, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights
AIA Document A101 8
Init.
reserved. “The are trademarks of The
American Institute of Architects, “American institute of Arch tects,” “AIA,” the AIA Logo, and "AIA Contract Documents"
expires on 02/25/2026, Is not for
American Institute of Architects. This document was produced at 11:22:19 5 T on 02/26/2025 under Order No.2114607688 which
To report copyright violations,
resale, is licensed for one-time use only, and may only be used in accordan be with the AIA Contract Documents® Terms of Service.
e-mail docinfo@aiacontracts.com.
(1448228681)
User Notes:
Serah9 1048.0 A
ARCHITECT'S PROJECT # 1531-24
se ath e e - Bean :
k
k Ea
8MEGPHLAUNIBC
k
T1.01
CV CONCEPT DESIGN STUDIO,308INC.
<tk—-E
600 £. ELLIS ROAD, SUITE
NORTON SHORES, MI 49441
PH, (231) 394-4835
FAX (231) T4637
CONCEPT DESIGN STUDIO, INC.
SECTION (00 01 01
PROJECT TITLE PAGE
PROJECT MANUAL
FOR
MUSKEGON POLICE DEPARTMENT - FIRST FLOOR RENOVATIONS
ARCHITECT'S PROJECT NUMBER: 1531-24.
CITY OF MUSKEGON
933 TERRACE STREET
MUSKEGON, MICHIGAN 49440
DATE: 01.23.2025
PREPARED BY:
GONCEPT DESIGN STUDIO, INC.
1531-24 / Muskegon Police 00 01/01 - 4 PROJECT TITLE PAGE
Department - First Floor
Renovations
SECTION (00 01 10
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
4.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
A. 0001 01 - Project Title Page
00 01 10 - Table of Contents
00 11 43 - Notice to Bidders
00 22 13 - Supplemental Conditons
00 24 12 - Proposal Section
00 24 13 -Description of Work
00 41 00 - Proposal Form
SPECIFICATIONS
2.01 DIVISION 01 -- GENERAL REQUIREMENTS
01 33 00 - Submittals and Substitutions
01 40 00 - Quality Requirements
01 42 19 - Applicable Standards
01 50 00 - Temporary Facilities and Contro
(2)
01 73 29 - Cutting and Patching
01 74 00 - Cleaning
01 78 23 - Operation and Maintenance Dat
poe
A. 017839 - Project Record Documents
2,02 DIVISION 02 -- EXISTING CONDITIONS
A. 0241 00 - Demolition
2.03 DIVISION 04 -- MASONRY
A. 0420 00 - Unit Masonry
2.04 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
A. 061053 - Miscellaneous Rough Covenin |
2.05 DIVISION 07 -- THERMAL AND MOISTU RE PROTECTION
A. 07 21 00 - Thermal Insulation
B. 07 92 00 - Joint Sealants
2.06 DIVISION 08 -- OPENINGS
A. 08 12 13 - Hollow Metal Frames
B. 08 14 16 - Flush Wood Doors
C. 0871 00 - Door Hardware
D. 08 80 00 - Glazing
2.07 DIVISION 09 -- FINISHES
A. 0921 16 - Gypsum Board Assemblies
09 22 16 - Non-Structural Metal Framing
moo®
09 30 00 - Tiling
09 51 00 - Acoustical Ceilings - USG
09 65 00 - Resilient Flooring
1531-24 / Muskegon Police 00 017/10 - 1 TABLE OF CONTENTS
Department - First Floor
Renovations
F. 0991 23 - Interior Painting
2.08 DIVISION 10 -- SPECIALTIES
A. 10 28 00 - Toilet and Bath Accessories
2.09 DIVISION 12 -- FURNISHINGS
A. 1221 13 - Window Blinds
B. 123200 - Manufactured Wood Casework
END OF SECTION
1531-24 / Muskegon Police 00 0110-2 TABLE OF CONTENTS
Department - First Floor
Renovations
GONGEPT DESIGN STUDIO, INC, Addendum 01
Date: January 31, 2025 Project #: 1531-24
Owner: Project Name:
City of Muskegon Muskegon Police Department
933 Terrace Street First Floor Renovations
Muskegon, MI 49440 933 Terrace Street
Muskegon, Mi 49440
Purpose: Addendum 01
or deletions
This document shall form part of the bidding docume nts. Changes, additions, clarifications
form, the
herein supersede the drawings and specifications. B dders shall include on the proposal
acknowledgement of this Addendum.
Attachments: None
Item #1 Pre-Bid Sign-in Sheet:
1. The following is a list of all attendees to he Pre-Bid walk-thru on January 30", 2025:
Alan Majeski AIA - Concept Design Stu dio amajeski@conceptdesignstudio.net
Lt. Bryan Prindle = - Muskegon PD bryan.prindle@shorelinecity.com
Matt Beerman - City of Muskegon matt.beerman@shorelinecity.com
Dave Brown - Muskegon Quality Builders dave@mabinc.com
Mark McLaren - Central Ceiling Wes t mark@centralceilingwest.com
Andy Zorn - Buck Construction andyz@cliffordbuckconstruction.com
Cassidy Brummel = - Compound Constru ction cbrumme|@comlbconstruction.com
Jay Picard - Bishop Heating jay@bishopheatingco.com
Chad Rehkopf - Orion Construction crehkopy@orionbuilt.com
Andy Yamaoka - Midwest Construct ion Group andy@midwestbuilt.com
Jeremy Padlo - Republic Services jpadlo@republicservices.com
Joe Ferske -~ Belasko Electric joef@belascoelectric.com
Steve Null - Tridonn Constructi on snull@tridonn.com
Item #2. Plenum Ceiling:
1. The existing ceiling cavity is a plenum an, id will remain a plenum. Note, all wiring in this space
must be plenum rated
Item #3 Existing VCT Flooring:
1. Include in your base bid the cost to rem ove all VCT. Assume everywhere below carpet and
exposed areas.
2. Provide an alternate price to leave all V¢ T, repair any loose or fill any openings and install
new LVT over it.
Addendum 01 BOO ELLIS ROAD, SUITE 508 * NORTON SHORES, Mi 49441
PHONE: 231.799.4838 + FAX: 231.799.4837
Page 1 of 1
e
CONCEPT DESIGN STUDIO, INC. Addendum 02
Date: February 10, 2025 Project #: 1531-24
Owner: Project Name:
City of Muskegon Muskegon Police Department
933 Terrace Street First Floor Renovations
Muskegon, MI 49440 933 Terrace Street
Muskegon, MI 49440
Purpose: Addendum 02
This document shall form part of the bidding documé nts. Changes, additions, clarifications or deletions
herein supersede the drawings and specifications. B dders shall include on the proposal form, the
acknowledgement of this Addendum.
Attachments: None
Item #1 Luminaire Legend Clarification ~ Drawin @ E1.02 (Not Reissued):
1. Luminaire Legend — Type Ato be the Syivar ia Luminaire specified to match owner’s
standard luminaires in the base bid. Delet = the equals for type A but will look at quotes on
Type A as volunteer alternates if submitted by Acuity, Cooper or Hubbell.
Item #2 Door $01. clarification:
1. Door S01 @ Stair $01 should be a Type ‘E ’ Door in a Type ‘1’ Frame. Glass to be rated to
match door.
Item #3 Subway Tile Clarification:
1. Subway wall tile to be equal to daltile ‘Ce lor Wheel Classic’ 4” x 8”. Color to be Matte Artic
White 0790. Provide Schluter trims at inside corner, floor and top of tile. Clear anodized finish.
ltem #4 Solid Surface Clarification:
1. Solid surface counter in Restroom 111 to be equal to Wilsonart ‘Brooklyn Concrete’ 9219GS
with an integral ‘white’ sink.
Item #5 Break Area Counter Tops
1. Break Area Counter laminate and backsplash to be selected from standard laminate colors.
Addendum 02 00 ELLIS ROAD, SUITE 508 *« NORTON SHORES, MI 49441
Page 1 of 1 PHONE: 231.799.4838 * FAX: 231.799.4837