Approved Agreements and Contracts 2025/05/13 South Breakwater Pier Gate Lease Amendment

View the PDF version Google Docs PDF Viewer

                                              CITY OF


                                  mg MUSKEGON
                          Agenda Item Review Form
                          Muskegon City Commission

Commission Meeting Date: May 13, 2025               Title: South Breakwater Pier Gate Lease
                                                    Amendment


Submitted by: Dan VanderHeide, Public Works         Department: Public Works
Director, Tim Kozal, Public Safety Director

Brief Summary:
Staff requests authority to sign the included amendment to the City's lease of U.S. Army Corps of
Engineers’ waterfront at Pere Marquette Beach to allow a pier gate to be installed.

Detailed Summary & Background:
About a year ago, the Public Safety Department submitted a grant to the U.S. Army Corps of
Engineers (USACE, commonly referred to as "the Corps") for a pier gate to be installed on the south
breakwater arm at Pere Marquette Beach. After a long deliberation, the Corps has awarded the
grant to Muskegon. Before the grant agreement can be signed and the pier gate installed, the lease
the City holds with the Corps that allows us to make specific improvements to property owned by the
Corps (including parts of Pere Marquette, Margaret Drake Elliot and the Muskegon Lake Channel)
needs to be amended to allow the gate to be installed. The attached lease amendment will make
those modifications.


The Public Safety Department will work with the Corps to execute the grant, while DPW may assist
with the gate installation depending on contracting method. Staff anticipates that specifically
authorized Parks staff (such as a Park Ranger) may operate the gate under the direction of Public
Safety.


Goal/Focus Area/Action Item Addressed:

Key Focus Areas:



Goal/Action Item:
2027 Goal 1: Destination Community & Quality of Life - Recognizable improvements to community
safety


Amount Requested:                                    Budgeted Item:
N/A                                                  Yes            No           N/A | X

Fund(s) or Account(s):                               Budget Amendment Needed:
N/A                                                  Yes            No           N/A   | X

Recommended Motion:
| move to approve staff to sign an amendment to the City’s lease of U.S. Army Corps of Engineers’
waterfront at Pere Marquette Beach to allow a pier gate to be installed.

Approvals:                                          Guest(s) Invited / Presenting:

 immediate Division
                                                     No
 Head

 Information
 Technology

 Other Division Heads

 Communication

 Legal Review
                                                          U.S.   ARMY CORPS      OF   ENGINEERS
                                                            LEASE       NO.   DACW35-1-16-3003


                           DEPARTMENT       OF   THE      ARMY
                 DETROIT    DISTRICT,        CORPS        OF ENGINEERS
                     SUPPLEMENTAL AGREEMENT NO.                     1
                    TO LEASE NO.           DACW35-1-16-3003
                         CITY   OF MUSKEGON,          MICHIGAN
            MUSKEGON HARBOR FEDERAL NAVIGATION PROJECT,                          MI


    THIS SUPPLEMENTAL AGREEMENT NO.                   1   is made and entered into
between the SECRECTARY OF THE ARMY, party of the first part,
hereinafter referred to as the Secretary or Government, and the
CITY OF MUSKEGON, MICHIGAN, party of the second part,
hereinafter   referred to       as   the   Lessee;


                            WITNESS                   ET    A:


     WHEREAS,    on 17   December 2012,          the Government granted to the
City of Muskegon,    the above numbered agreement,                        for a period of
twenty-five (25) years beginning 1 October 2016 and ending 30
September 2041 at the Muskegon Harbor Federal Navigation
Project, MI, as more specifically described in said lease.

     WHEREAS,    The Lessee has requested to construct,                          maintain,
and operate a removable seasonal gate on the US South Breakwater
to deter pedestrian use in times of adverse weather conditions.

     NOW THEREFORE,      Lease no.         DACW35-1-16-3003              is hereby amended
in the    following respects,        but   in no others:


     1. Condition No. 36 b. is amended by DELETING therefrom,
“USACE Grand Haven Resident Office. The point-of-contact for
coordination is Elizabeth Wilkinson, Resident Engineer
(telephone 616-240-7989) and can also be reached by email at
elizabeth.n.wilkinson@usace.army.mil.” and SUBSTITUTING in lieu
thereof, “U.S. Army Corps of Engineers’ Operations Project
Manager of the Grand Haven Office. The current Operations
Project Manager can be reached by phone at (616) 842-5510
x25523.”


     2.    ADDING Condition 36 j.           ” The Lessee is authorized to
construct, operate, and maintain a gate on the U.S. South
Breakwaters. This removable gate may be used to deter pedestrian
access to the breakwater during times of inclement weather.”

     3.    ADDING Condition 36        k.    “Appropriate          safety measures must
                                     Page    1   of   3
                                                     U.S.    ARMY CORPS OF ENGINEERS
                                                       LEASE NO.       DACW35-1-16-3003


be employed during all work or maintenance activities performed
by the Lessee. The Lessee activities must not degrade the
condition of the premises or cause interference with the
operations and maintenance of the Federal project, including
access to the Federal navigation structures.”

     4. ADDING Condition 36 1. “USACE maintenance activities
require a minimum of a 60” wide opening to access the pier when
conditions allow. The exact placement, location and construction
will require coordination with and approval by USACE as outlined
in Condition No.   36 b.”


                         m. “In the event of construction or
    5. ADDING Condition 36
maintenance on the U.S. South Breakwater by the Department of
the Army, the Permittee may be required to remove the gate until
completion of such actions.”

     6.   ADDING the attached Exhibit “D”,             in its entirety,        hereto
and made part of the   lease.


     EXCEPT for the revision above, the terms and conditions of
the lease shall remain unchanged and in full force and effect.

     IN WITNESS WHEREOF,    I have hereunto set my hand by
authority of the Secretary of the Army, this                    27th
day of    June                  ,   2025
                                             \




                                                         t signed by
                                       SHELTON.ANDRE os
                                                     SHELTON.ANDREW.M.151639851

                                       W.M.1516398511 Date:
                                                      | 2025.06.27 10:30:09 -04'00
                                       Andrew M.            Shelton
                                       Chief,        Real Estate Tech Branch
                                       Real Estate Contracting Officer




                                Page    2   of   3
                                                  U.S.   ARMY   CORPS   OF ENGINEERS
                                                    LEASE NO.     DACW35-1-16-3003


     The above instrument,   together with all the conditions
thereof, is hereby accepted this             26th                 day of
        June             , 20 25




                                    CITY OF MUSKEGON,            MICHIGAN




                                     . iyAff
                                    (Signature)




                                    Dan VanderHeide
                                    {Printed Name)




                                    Director of Public Works
                                    (Title



                                    June 26, 2025